Here is the information on the elevator project in the Cathedral of Learning:
Cathedral of Learning Elevator Upgrades
Listed on the National Register of Historic Places, the
42-story Cathedral of Learning is the tallest educational building in the
Western hemisphere. The current elevator
control system and elevator equipment are not capable of efficiently handling
the large volume of passengers passing through the Cathedral each day. As part of the University’s 12-Year
Facilities Plan, the Cathedral elevators are scheduled to be modernized to improve
traffic flow through the building. The original Cathedral elevator system,
manufactured by Westinghouse, was installed in 1931. The elevators were upgraded in 1971 and again
in 1998, but those upgrades were of limited scope and provided marginal improvement.
Over the years, additional efforts to
improve service included reducing the number of stops for many elevators,
requiring passengers to travel to a floor near their destination and then walk
up or down a floor or two. The original
Westinghouse hoisting machines, which move the elevators through the shafts,
are still in use today and are operating significantly beyond their expected
service life. The new system will take
advantage of new emerging destination based elevator technology to significantly
decrease the time to destination and increase reliability of the system.
This project will provide a comprehensive
modernization of the building’s 8 main elevators with what is referred to as a “destination
based” dispatching system. With a destination
based system, passengers enter their desired destination on a kiosk or keypad
and are immediately directed to the elevator that will take them to their
selected floor. The system serves the
building more efficiently by grouping passengers according to their
destination, thereby reducing the number of stops each car will make. This will allow many of the previously
deactivated floor stops to be reactivated, providing greater elevator coverage
to more floors and direct access to floor destinations for most passengers. Touch screen kiosks will be installed on the
ground and first floors, and the remaining floors will be fitted with smaller
keypads. There will be no floor buttons
to select once passengers enter the car.
Instead, an in-car display will indicate the stops to be served during
that specific trip. The modernization
includes replacing the elevator control system, hoisting equipment, doors, and cabs
and installing new safety devices. Some
lobbies will also be modified as openings are reactivated. The shuttle elevator that services floors 36
to 40 will also be replaced. When
completed, the modernization will provide greatly improved efficiency in
handling capacity and significantly reduced wait times. This system is expected to also reduce
congestion on the ground and first floor elevator lobbies during peak demand
times and significantly improve the reliability of the elevators. Mechanical
and electrical upgrades will also be completed to support the new system and to
meet current codes. The new system will also
comply with the Americans with Disabilities Act (ADA) and will be more energy
efficient.
The modernization of the elevators has already begun. The contractor is currently aligning the
existing rails which the cars ride on.
This work should be complete by October.
The work to modernize the elevator cabs and control system will begin in
December, 2014 and all work is scheduled to be complete in the spring of
2016. During this period, two (2)
elevators will be taken out of service at a time in order to perform the
modernization. Each group of two
elevators, one high rise and one low rise, is slated to take three (3) to four
(4) months to complete. Final project
completion is expected in the spring of 2016.
After each group of elevators is complete, there will be a transition
when both the old call button system and the new destination system kiosks and
keypads will be in operation. It will be
important during this transition to pay close attention to which elevator to
board. Facilities Management will make
every effort to ease this transition through directional signage and
informational updates as the project progresses. The work in the elevator shafts and machine
rooms will take place primarily during the day, but disruption should be
minimal. The lobby work to reactivate
door openings will take place from 10:00 p.m. to 6:00 a.m. The progress of the modernization can be
followed on Facebook by searching University of Pittsburgh Cathedral Elevator
Modernization and Twitter @Cathedralelev.
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.